Construction Progress

Strong progress has continued at 208 Bankwood Road, with the development now moving further through the internal finishing and exterior completion stages.

Window shrouds have now been installed, further completing the external appearance of the units. With the main exterior works now well advanced, scaffold removal is expected to take place in the coming days, marking another key milestone for the project.
Internally, doors and finishing lines are now being installed across the units as the homes progress through the next stage of interior completion.

Overall, the project is progressing well, with the focus now shifting toward final internal finishing works and preparing the external areas for the next stage of site works.

What's Next

Over the next month, the focus will be on progressing the next stage of internal and external works, including:

• Scaffold removal
• Progression of internal fit-off works
• Landscaping preparation
• Driveway preparation
• Installation of internal fencing