Hamilton
Last Updated: 4th November 2026
Excellent progress continues at 30 De Vere Crescent, with the development now moving through the exterior finishing and internal fit-out stages.
Brickwork to the main buildings is now complete, with only the brickwork to the boundary fencing remaining. Installation of the remaining exterior cladding is currently underway.
Internally, the plumbing and electrical first-fix works have now been completed. With these services in place, the homes are ready to progress into the insulation stage.
Over the coming period, work will focus on progressing both the exterior and internal works:
• Completion of the remaining exterior cladding
• Completion of the brickwork to the boundary fencing
• Installation of insulation
• Progression into internal lining works following insulation